Construction Change Order Form Template for Excel
A construction change order is a signed amendment that records what is changing, what it costs, and how the schedule moves. This guide explains the documents, the form fields, a repeatable approval process, and how the Excel template prices materials, labor, and equipment before you send the form for signature.
What a change order is — and what it is not
A change order handles work beyond the agreed contract scope. The contractor prepares the form showing effects on schedule and budget, and the owner approves it before new work begins. The Associated General Contractors of America describes this as an official change to the original scope or terms agreed by owner, contractor, and designer.
Keep three documents distinct. A change order request is a proposal with pricing; the schedule does not move until the owner responds. A change order is the signed amendment that folds the new work, price, and dates into the contract. A construction change directive is different: the owner puts an instruction in writing telling the contractor to go ahead immediately, even though cost and schedule effects have not yet been agreed, leaving those to be resolved afterward under the contract.
Why change orders happen
Changes add time, cost, and complexity. Without a clear process they create confusion and hidden costs. Four common causes tend to appear at different stages:
- Unforeseen site conditions, often during excavation or demolition — rock in a footing trench delays a foundation pour; old wiring behind remodel walls adds electrical scope.
- Owner-requested changes, often during framing and rough-in while walls are open — a new kitchen island with added circuits means more electrical work and a moved rough-in inspection.
- Design errors or omissions, often when trades begin installing — a beam conflicting with a duct run stalls mechanical rough-in until the designer issues a fix.
- Code or inspector requirements, often at inspections — added fire blocking sends the framer back, and insulation and drywall wait for reinspection.
Record the affected phase and the next task waiting on it in the impact section of the form.
What to include on the form
A complete form makes the change identifiable and signable. Include project and request details such as Project ID, requestor name, request date, and Change Order ID. Describe how the request differs from the original scope, explain why it is needed, and state the proposed action with steps, hours or days, and any scope adjustments.
For impact, cover scope, budget, timeline, resourcing, communications, and other effects. For timeline, state working days added or removed and which tasks or milestones move, so the owner approves the date change as well as the price. Estimate costs for materials, labor, and equipment using contracted rates and the applicable profit margin; check the contract's change order clause before pricing markup. End with an approval signature confirming the owner agrees to the approach, impacts, and costs.
A repeatable process from request to schedule update
Use the same path for every change: document it when it arises with photos, the request, who asked, and written notice within the contract window; price it from saved databases; complete the form including schedule impact in working days and affected tasks or milestones; obtain signatures before work starts, since verbal approval leaves price and days exposed to dispute; update the schedule and notify affected crews and subs; file the signed form and log it by number for closeout totals and billing questions.
Worked example: a kitchen island request arrives after rough-in is scheduled. Photograph the layout, price two new circuits plus an extra electrician day, and list a one-day impact. After signature, rough-in runs a day longer, the rough-in inspection moves back a day, and drywall starts a day later. After approval, save a schedule baseline before moving dates, link affected tasks with dependencies, check whether the added day lands on the critical path, and request confirmation from assigned subs so a decline surfaces before an inspection is booked.
How the Excel template works
The template has an Instructions tab, a Change Order Form tab, a Bid Sheet tab, and three customizable databases for Material, Labor, and Equipment. First replace generic database data with your own rates, then save the file as a template for future jobs.
Material: add or replace Material Types; choosing one on the Bid Sheet fills in unit of measurement and unit price automatically. Labor: add up to 24 Labor Types with hourly rate and burden — payroll taxes, insurance, and benefits on top of wages, or 0% if burden is excluded. The Man Day rate is calculated from rate plus burden and should not be edited. Equipment: add Equipment Types; the Bid Sheet calculates cost from the listed equipment cost and quantity.
On the Bid Sheet, enter Project Name and CO# at the top; those populate the form. In Material, pick a type, enter quantity, and the total calculates; an Adjustment column can correct a total, using a negative number for a discount, and sales tax should reflect your local rate. In Labor, pick a type, enter crew size and days; new labor types cannot be typed directly into the Bid Sheet. In Equipment, pick a type and quantity; new equipment types likewise come only from the database. The Summary shows base cost per section, totals with and without profit, total profit, and a rounded total that feeds the form. Set profit with the global setter or override it per section where the contract requires a different rate; overriding replaces the linked formula, which can be restored from the Instructions tab. Complete the free-text fields on the Change Order Form, then print or save as PDF to send.
Best practices checklist
Get every change in writing and signed before work starts, including small ones raised on a site walk. Number change orders sequentially and keep a running log in the job file. Describe each change specifically enough that someone outside the job could understand it a year later. Price from saved databases so every bid uses current rates. State schedule impact in working days even when it is zero. Review the contract's change order clause at kickoff, including notice window, markup, and who signs. Use the same template on every job so owners and subs know what to expect.
| Document | Who issues it | Effect on schedule and contract |
|---|---|---|
| Change order request | Contractor or sub | Proposal and pricing; schedule unchanged until owner responds |
| Change order | Both parties sign | Signed amendment; new work, price, and dates become part of the contract |
| Construction change directive | Owner | Written go-ahead to start immediately; cost and time are resolved afterward under the contract |
Distinctions are based on the definitions in the guide; contract terms govern in any specific job.
| Bid Sheet section | What you enter | What calculates automatically |
|---|---|---|
| Material | Material Type and quantity; optional adjustment | Unit of measurement, unit price, line total, material total |
| Labor | Labor Type, crew size, and days | Labor cost, total man days, profit per man day |
| Equipment | Equipment Type and quantity | Profit and total from listed equipment cost |
| Summary | Sales tax rate and profit settings | Section base costs, totals with and without profit, rounded form total |
Labor and equipment types must be created in their databases; material entries typed directly overwrite the database link.
Frequently asked questions
What is the difference between a change order request and a change order?
A request is the proposal and price for work outside the contract. A change order is the signed amendment that makes that work, price, and schedule effect part of the contract.
What is an example of a change order in construction?
A homeowner adds a kitchen island with two new circuits after rough-in is scheduled. The change covers added material and an extra electrician day, plus a one-day delay to the rough-in inspection and drywall start.
Who pays for a change order in construction?
Payment follows the contract language and what caused the extra work. An owner-requested addition is normally charged to the owner, a contractor's own mistake is normally absorbed by the contractor, and unexpected site conditions are handled as the contract directs.
How much markup should go on a change order?
Your contract or company policy sets markup, so check the change order clause first. The template described here defaults to a 25% global profit margin that can be adjusted on the Bid Sheet.
Can work start before a change order is signed?
Wait for a signed change order whenever you can. The exception is a construction change directive, where the owner orders work in writing and price or time is settled later under the contract.
Should I use Excel or PDF for change orders?
Use both: build and price in Excel, then save the Change Order Form as a PDF to send. Keep the Excel file as the working copy for the job log.